Trail Bridge Sub-Sector Program

Proyecto terminado

The project supports the Government of Nepal to institutionalize trail bridge building under the new federal structure. Due to the ongoing state restructuring process, Swiss support is required for a last phase to ensure the transfer of the institutional and human capacity built-up in trail bridges over the past four decades to the new state and local governments. Walking remains a major mode of travel in Nepal, and trail bridges are still essential for people to access basic public services

Región/País Tema Período Presupuesto
Nepal
Empleo y desarrollo económico
Governance
nothemedefined
Apoyo a empresas e inclusión económica
Desarrollo rural
Descentralización
01.12.2019 - 30.11.2023
CHF  9’400’000
Contexto Reduced physical accessibility and connectivity for the people living in the remote areas of Nepal has resulted in a high incidence of poverty, which contribute to income disparity and social discrimination with respect to their access to public services. While Nepal till recently made impressive gains in the field of trail bridge building, the re-organisation of the government structures has led to dispersement of the trained human resources.  The newly established local and State governments lack institutional and technical capacities to implement Trail Bridges building programme
Objetivos Nepalese citizens economically and socially prosper through better physical connectivity
Grupos destinarios

More than 4.3 million additional people will benefit from 2400 new trail bridges for safer crossings;

About 5.5 million person days (p-days) employment generated with at least 2.7 million p-days targeted to disadvantaged groups and 2 million p-days targeted for women in the construction of trail bridges;

Private sector (consultants, non-government organizations, fabricators, contractors);

All 753 local governments, 7 State Governments and the Federal Government will benefit from enhanced capacities to implement and enforce the trail bridge strategy in a federal context.

Efectos a medio plazo

The three expected outcomes of the programme are:

  • Nepali citizens use Trail Bridges to have safe and equitable access to basic services and employment opportunities.
  • Governments at all levels (Local, State and Federal) implement Trail Bridge Strategy to construct and maintain trail bridges equitably.
  • Private sector engages in effective delivery of good quality Trail Bridges.
Resultados

Resultados previstos:  

Output 1.1 & 1.2: Users Committees strengthen their capacity to organize and build trail bridges.

Output 2.1& 2.2: Department of Local Infrastructure strengthens its capacity to update Trail Bridge related policy frameworks; and to plan, budget, procure and implement technically complex Trail Bridges.

Output 2.3& 2.4: State and Local Governments strengthen their capacity to build and maintain trail bridges equitably.

Output 3.1: Consultants/contractors and fabricators strengthen their capacity to effectively and efficiently provide services for the construction of good quality Trail Bridges.

Output 3.2: Engineering institutes produce qualified technical personnel in Trail Bridge sector.


Resultados de las fases anteriores:  

From mid-2009 to mid-2018, an additional 8 million people benefited from 3175 new trail bridges, on average gaining 2.3 hours per person on every 2 way trip they make using a trail bridge. The main reasons for people to cross the bridges were to perform household chores (30%), go to schools (30%), markets (17%), social functions (12%) and access health facilities (10%). Over 1.3 million people cross the bridges daily. Over 7.9 million person days of employment were generated during the construction (Source: Trail Bridge Strategy Information System 2018).

There is increased record of school attendance rates (16%), and number of patients accessing health facilities increased by 23% in the areas. Women’s representation in the Users’ Committees of Trail Bridges was 46% while the representation for discriminated groups was 67%. New shops or markets came up at 20% of the trail bridge sites creating new economic opportunities. Four consortia of Nepali private consultants and non-government organizations are providing technical services in 5 regions.17 private steel fabricators are providing services in 4 states, while 7 Engineering Institutes are offering trail bridge courses in their curriculum.  (Source: Annual Project Report 2017).


Dirección / Officina Federal responsable COSUDE
Crédito Cooperación al desarrollo
Contrapartes del proyecto Contraparte del contrato
Sector privado
Organización suiza sin fines de lucro
  • HELVETAS Swiss Intercooperation
  • Sector privado extranjero Sur/Este


Coordinación con otros proyectos y actores Synergies with in principle all e+i projects. Particular synergies with PSD, MSD, EPS projects. Synergies with Quality Assurance Division in connection with the DCED Results Measurement Standard which is increasingly applied within SDC.
Presupuesto Fase en curso Presupuesto suizo CHF    9’400’000 Presupuesto actual suizo ya emitido CHF    9’200’000
Fases del proyecto

Fase 5 01.12.2019 - 30.11.2023   (Completed)

Fase 4 01.08.2014 - 30.11.2019   (Completed) Fase 3 01.01.2011 - 30.09.2014   (Completed)